Inclinometers
How do you store the control cable?
Improper coiling of any electrical cable twists the conductors inside the cable and will eventually cause reliability problems. Cable reels are one solution to this problem, but are typically used only with longer lengths of cable. With shorter lengths of cables, it is probably easiest to coil the cable by hand, either in figure-8s or in over-under loops. You can find a drawing of this in our inclinometer probe manual. Some DOTs report that they use two traffic cones to guide their figure-8 coils. Other people use a large laundry basket to hold their over-under loops. Still others have reported mounting garden hose holders on a backpack, one at the top and one at the bottom, and then making figure-8 loops. With longer lengths of cable, cable reels become more practical. There are two types of cable reels: storage reels and slip-ring reels. Storage reels are simply a place to store the cable. To use the cable, you must unreel it first. Some people use garden hose reels for this purpose. Note that any reel should have a hub diameter of about 12 inches (300 mm) to avoid small bends in the cable. Storage reels can be heavy, but then, so is the cable. Slip-ring reels provide an electrical connector, so that you have full operation of the cable while it is on the reel. Slip-ring reels tend to be expensive and heavy. Slope Indicator’s slip-ring reel weighs 37 pounds (16.5 kg). Thus is it not very portable. Mines and other sites with very deep inclinometer installations sometimes use motorized reels. These are even larger, heavier, and more expensive. They also have automation features, such as controlling the depth of the probe.
Can I replace the wheels of my probe if they are worn out?
Yes, but this is not a simple task, and it can cause a shift in the calibration of the probe. Normally we recommend that this repair be performed at the factory, since the probe can be recalibrated after the repair. The repair requires kit number 50302555, which contains a wheel yoke with wheels, two springs, and four roll pins, so you normally need two kits per probe. If you are interested in replacing the wheels yourself, download these instructions to learn more.
What kind of inclinometer test stand will help me monitor the health of my probe?
ASTM now has a practice that lists the necessary equipment and method for verifying the calibration of your probe. However, in many cases, your data and graphs can go a long way toward satisfying your verification needs:
- The bottom 10 feet of your casing should be installed in stable ground. This way, you are assured of a stable reference. (To be more exact, we recommend that you install 5-reading intervals of casing in the stable ground, thus with metric casing, this would be 2.5 meters.)
- Since the bottom of the casing is stable, your surveys should show no movement at all within that ten feet. Any movement that you see is error. Thus you have an in-situ test stand.
- With this in-situ test stand, you don’t need to perform any explicit tests. The information you need to check your probe is embedded in your readings.
- This in-situ method of checking the probe is better than the test stand method for several reasons: First, the installed casing is more stable than any test stand on the surface. Second, the information is embedded in each inclinometer survey, so it won’t get lost. Third, the embedded information shows the condition of the probe at the exact time of the survey.
What are the pinouts for the Lemo connector on the indicator-end of the control cable?
This information is provided for those who have already contacted the factory and decided to do a repair themselves. Wire colors vary according to the age of your cable, so you’ll have to use an ohmmeter to determine which wire you have. Note that this information is for making repairs to solder joints within the Lemo connector, which is on the indicator end of the control cable. Please do not attempt to make repairs to the connector on the probe end of the cable. It is extremely difficult to reassemble this connector properly.

Grout Mix for Hard and Medium Soils
| MATERIALS | WEIGHT | RATIO BY WEIGHT |
|---|---|---|
| Portland cement | 94 lb (1 bag) | 1 |
| Water | 30 gallons | 2.5 |
| Bentonite | +/- 25 lbs. (See Notes Below) | 0.3 |
| Mix cement with water first. Then mix in the bentonite. Adjust the amount of bentonite to produce a grout with the consistency of heavy cream. If the grout is too thin, the solids and the water will separate. If the grout is too thick, it will be difficult to pump. The 28 day compressive strength of this mix is about 100 psi, similar to hard clay. The modulus is 10,000 psi. | ||
Grout Mix for Soft Soils
| MATERIALS | WEIGHT | RATIO BY WEIGHT |
|---|---|---|
| Portland cement | 94 lb (1 bag) | 1 |
| Water | 75 gallons | 6.6 |
| Bentonite | +/- 39 lbs. (See Notes Below) | 0.4 |
| Mix cement with water first. Then mix in the bentonite. Adjust the amount of bentonite to produce a grout with the consistency of heavy cream. If the grout is too thin, the solids and the water will separate. If the grout is too thick, it will be difficult to pump. The 28 day compressive strength is about 4 psi, similar to very soft clay. | ||
Notes
- It is not really practical to try to match the strength of the grout to the strength of the soil, since the properties of grout and soil are so different. The cement-water ratio controls the strength of the grout. To decrease the strength of the grout, add more water.
- Drillers are accustomed to mixing water and bentonite first, but this will not allow you to control the water-cement ratio. Mix water and cement first. Then add bentonite. There is no particular amount of bentonite that you must add. The thickness of the grout varies with water, temperature, and agitation, so the amount of bentonite required will vary.
- The quantity of the third ingredient to be added must be adjusted to obtain a suitable consistency. A watery mix is NOT acceptable. A mix that is too thick cannot be pumped. The Marsh funnel number of the liquid grout should be about 55 seconds +/- a few seconds.
- If you mix cement and water first, the amount of bentonite has to be adjusted. The amount is rarely ever equal to exactly 25 lbs. The final quantity also varies with the type of bentonite used, the method of mixing and the pH of the water.
- If you mix bentonite and water first, the mix usually gets so thick with one bag of cement that it cannot be pumped. There is also a high risk of a flash-set. The cement content must usually be lowered. That results in a higher w/c ratio, lower strength and probably a higher permeability.
- If the mix is left too watery, not only do you get shrinkage, but segregation occurs: cement on the bottom, then bentonite and water on top (bleed). This is not acceptable.
Better Ways to Counter Buoyancy
- Suspend a steel pipe or drill rods inside the casing. For the best results, suspend the pipe just an inch or so off the bottom cap of the casing.This ensures that the steel pipe remains straight and avoids resting the full weight of the pipe on the bottom cap. As the casing rises to meet the pipe, the down force of the pipe is activated to keep the casing in place. The main drawback to this method is that you must use the drill rig to suspend the pipe or you must return with the drill rig to retrieve the pipe. A variation is to rest the pipe on the bottom cap, which you must reinforce.
- Pre-install an anchor at the bottom of the casing. Simple prong anchors or packer types have been used. Slope Indicator has produced several prototypes of such anchors. Different soils may require different types of anchor.
Pre-attach a weight to the bottom of the casing. This method requires a weight, a safety line to prevent casing from sinking, a borehole drilled deeper to accommodate the weight, and calculation of the uplift force. It is best used in shallow boreholes. - Grout the borehole in stages. The uplift force of grout varies with the height of the grout column. If the column is short, the uplift force is low and the casing can be held in place by its own weight or with very little down-force applied from the top. When the grout sets, the bottom cap is isolated from the column of grout and there is no surface for the uplift force to act on. No more than two or three meters to 3 m need to be grouted in the first stage. If the normal bentonite/cement grout is used it needs to set for at least 12 hours before second-stage grouting. Avoid use of a quick-set grout, since the heat of hydration could melt and deform the plastic. The two stages can be placed via an outside tremie pipe. Alternatively the first stage can be placed before lowering the casing, provided that all is done efficiently so that there is no chance of the grout setting prematurely. If grout valve method is used, first stage grouting can be done through the valve, and then the valve is abandoned. An outside tremie pipe for the second stage is lowered with the casing, with its bottom at the level planned for the top of the first stage. After first stage grouting, the excess is flushed out via the tremie pipe, and then this is raised until the first stage has set.
- Fill the casing with drilling fluid that is heavier than the grout. This is a sure and easy method, but requires disposal of the drilling fluid.
The Worst Way to Counter Buoyancy
Unfortunately, the easiest way to keep the casing in place – holding the casing down from the top – is also the worst way. The uplift force acts on the bottom of the casing, so if the casing is held in place from the top, the casing goes into compression. When the casing goes into compression, it tends to snake from side to side in the borehole. This problem is particularly severe in large diameter boreholes and in deep installations, where the uplift force is largest and where portions of the borehole may be enlarged. Snaked casing increases the potential for:
- Kinked or Separated Casing: The combination of compressive force and eccentric loading (due to snaking in enlarged diameter boreholes) can produce strong bending moments in the casing. In some severe cases, this bending moment has caused snap-together joints to fail where the glue-and-rivet joints do not.
- Depth Errors: In snaked casing, slight changes or errors in the positioning of the probe will produce reading errors. The larger the curvature, the larger the error. For example, if the change of inclination between adjacent reading increments is two degrees, and the probe is positioned 25 mm from the correct depth, the resulting error in displacement would be 1 mm.
How does inclinometer casing behave in soft soil?
Erik Mikkelsen says:
I have heard this concern voiced from time to time, but the evidence from measurements in slopes and landslides suggest that it should not be a big concern, particularly in soft (loose) soil.
In soft soils, shear displacements are more distributed than in harder soils. For example, the shear zone in a basalt landslide complex was measured to be 15 inches thick using special inclinometer procedures. On the south Oregon coast (Arizona Inn landslide) in mélange, the shear zone is on the order of 2 to 3 feet thick after a major rupture and repair work. Measurements at the toe of an embankment in soft silts and clays next to the Puyallup River in Tacoma indicated a shear zone of 4 to 6 feet.
Based on the experience above, I think that within the measurable range of the inclinometer system, the stiffness of the inclinometer casing will not appreciably redistribute displacements. A significant rupture occurs most likely on a plane or a thinner zone, but that is the beyond the range that the inclinometer can measure. (The casing simply closes and does not allow passage of the probe).
Inclinometer casing made from ABS is relatively weak compared to the ground and is quite ductile. It does not normally crack due to excessive deformation, it cold flows. It would be difficult to come up with a “softer” material that would meet production, installation and tracking requirements.
There are two other significant factors in soft soils. Drilling of the borehole can alter the conditions around the installation. Loose soil can densify and cave, changing the natural conditions. The stiffness of the backfill also has an effect, since it typically occupies 75% of the borehole cross-sectional area. Grout stiffness is probably a greater issue than the ABS casing stiffness. Not much information is available on design and characteristics of soft cement-bentonite grout as far as I know. In soft soil the “instrument disturbance factor” can be significant.
Finally, even if there is some redistribution of displacements due to grout and casing stiffness and borehole disturbance, the inclinometer will measure the correct total amount, but over a longer interval of the borehole. Also, the true profile of the casing in the shear zone cannot be defined by ordinary methods. Special techniques using 3-inch reading intervals and special calculation methods must be used.
How can I prevent the water in my inclinometer from freezing?
To prevent the water from freezing we recommend filling the casing with a water + propylene glycol solution. Propylene glycol is a non-toxic antifreeze fluid. Although this solution should be harmless, always wash off the probe and cable after use.
Here is a table showing the freezing point for various solutions. The table is provided by engineeringtoolbox.com.
| FREEZING POINT – PROPYLENE GLYCOL AND WATER SOLUTIONS | ||||||||
|---|---|---|---|---|---|---|---|---|
| % Solution by mass | 0 | 10 | 20 | 30 | 40 | 50 | 60 | |
| Temperature | F | 32 | 26 | 18 | 7 | -8 | -29 | -55 |
| C | 0 | -3 | -8 | -14 | -22 | -34 | -48 | |
Should I used large, medium, or small diameter casing?
Casing is designed to deform with movement of the adjacent ground or structure. The useful life of the casing ends when casing curvature forces the inclinometer probe out of the grooves in the casing. Continued movement of the ground pinches or shears the casing, and eventually prevents passage of the inclinometer probe. Large diameter casing (85 mm, 3.34 inch) is suitable for landslides and long term monitoring. It is also appropriate for monitoring multiple shear zones or very narrow shear zones. Large diameter casing is required when the horizontal probe is used. Medium diameter casing (70 mm, 2.75 inch) is suitable for construction projects. It can also be used for slope stability monitoring when only a moderate degree of deformation is expected. Small diameter casing (48 mm, 1.9 inch) is suitable for applications where small deformations are distributed over broad zones. It is generally not installed in soils.
Is a bentonite grout, such as Volclay, suitable for backfilling around inclinometer casing?
It is important to have some cement in the mixture for dimensional stability. Bentonite alone will never set and its volume varies with moisture levels.