Inclinometer Casing
Inclinometer casing is a special purpose pipe used in inclinometer installations. It performs three functions:
- It maintains access for the inclinometer probe, allowing it to obtain subsurface measurements.
- It controls the orientation of the probe via internal grooves.
- It conforms to movement of the surrounding ground.

QC Casing Video
Casing Diameter & Groove Shape
- 85 mm / 3.34 inch casing is the largest diameter. It is suitable for all uses and especially recommended for landslides and long-term monitoring. It is also appropriate for monitoring multiple shear zones or very narrow shear zones.
- 70 mm / 2.75 inch casing is suitable for construction projects. It can also be used for slope stability monitoring if only a moderate degree of deformation is expected.
- 48 mm / 1.9 inch casing is used only deformations are expected to be very small and are distributed over broad zones. It is generally not installed in soils.
Groove Shape
The accuracy of inclinometer measurements is directly influenced by the quality of the casing grooves. The best grooves provide a regular, flat surface for the wheels of the probe.
The grooves should be slightly wider than the wheels, to permit some side to side movement as the probe passes through curves. If the grooves are too tight, the wheels will climb out of the grooves and degrade the reading.
Coupling Style





Inclinometer Casing Accessories


Grout Mixes for Inclinometers
Materials | Weight | Ratio by Weight |
---|---|---|
Portland cement | 94 lb (1 bag) | 1 |
Water | 30 gallons | 2.5 |
Bentonite | +/- 25 lbs. (See Notes Below) | 0.3 |
Mix cement with water first. Then mix in the bentonite. Adjust the amount of bentonite to produce a grout with the consistency of heavy cream. If the grout is too thin, the solids and the water will separate. If the grout is too thick, it will be difficult to pump. The 28 day compressive strength of this mix is about 100 psi, similar to hard clay. The modulus is 10,000 psi. |
Materials | Weight | Ratio by Weight |
---|---|---|
Portland cement | 94 lb (1 bag) | 1 |
Water | 75 gallons | 6.6 |
Bentonite | +/- 39 lbs. (See Notes Below) | 0.4 |
Mix cement with water first. Then mix in the bentonite. Adjust the amount of bentonite to produce a grout with the consistency of heavy cream. If the grout is too thin, the solids and the water will separate. If the grout is too thick, it will be difficult to pump. The 28 day compressive strength is about 4 psi, similar to very soft clay. |
- It is not really practical to try to match the strength of the grout to the strength of the soil, since the properties of grout and soil are so different. The cement-water ratio controls the strength of the grout. To decrease the strength of the grout, add more water.
- Drillers are accustomed to mixing water and bentonite first, but this will not allow you to control the water-cement ratio. Mix water and cement first. Then add bentonite. There is no particular amount of bentonite that you must add. The thickness of the grout varies with water, temperature, and agitation, so the amount of bentonite required will vary.
- The quantity of the third ingredient to be added must be adjusted to obtain a suitable consistency. A watery mix is NOT acceptable. A mix that is too thick cannot be pumped. The Marsh funnel number of the liquid grout should be about 55 seconds +/- a few seconds.
- If you mix cement and water first, the amount of bentonite has to be adjusted. The amount is rarely ever equal to exactly 25 lbs. The final quantity also varies with the type of bentonite used, the method of mixing and the pH of the water.
- If you mix bentonite and water first, the mix usually gets so thick with one bag of cement that it cannot be pumped. There is also a high risk of a flash-set. The cement content must usually be lowered. That results in a higher w/c ratio, lower strength and probably a higher permeability.
- If the mix is left too watery, not only do you get shrinkage, but segregation occurs: cement on the bottom, then bentonite and water on top (bleed). This is not acceptable.
Countering Casing Buoyancy
Grout backfill has a higher density than water-filled casing. During installation, when the grout is still a fluid, it exerts an uplift force on the bottom cap of the casing. This uplift force is greater than the down force exerted by water-filled casing. The net uplift can be calculated as the density of grout minus the density of water filled casing x depth of casing x area of bottom cap. Lateral forces do not contribute to uplift.
The density of water-filled casing is about 62.4 pounds per cubic foot or 1000 kg per cubic meter. The density of ABS casing and the density of water are nearly the same. The density of bentonite-cement grout is about 80 pounds per cubic foot or 1280 kg per cubic meter. The area of the bottom cap of 2.75" (70mm) inclinometer casing is 0.0412 square feet or 3.8485E-3 square meters. Thus if the bottom cap is 100 feet deep, the uplift pressure on the 2.75 inch bottom cap will be about 72.5 pounds or 32.3 kg.
Unfortunately, the easiest way to keep the casing in place - holding the casing down from the top - is also the worst way. The uplift force acts on the bottom of the casing, so if the casing is held in place from the top, the casing goes into compression. When the casing goes into compression, it tends to snake from side to side in the borehole. This problem is particularly severe in large diameter boreholes and in deep installations, where the uplift force is largest and where portions of the borehole may be enlarged. Snaked casing increases the potential for:
- Kinked or Separated Casing: The combination of compressive force and eccentric loading (due to snaking in enlarged diameter boreholes) can produce strong bending moments in the casing. In some severe cases, this bending moment has caused snap-together joints to fail where the glue-and-rivet joints do not.
- Depth Errors: In snaked casing, slight changes or errors in the positioning of the probe will produce reading errors. The larger the curvature, the larger the error. For example, if the change of inclination between adjacent reading increments is two degrees, and the probe is positioned 25 mm from the correct depth, the resulting error in displacement would be 1 mm.
- Suspend a steel pipe or drill rods inside the casing. For the best results, suspend the pipe just an inch or so off the bottom cap of the casing.This ensures that the steel pipe remains straight and avoids resting the full weight of the pipe on the bottom cap. As the casing rises to meet the pipe, the down force of the pipe is activated to keep the casing in place. The main drawback to this method is that you must use the drill rig to suspend the pipe or you must return with the drill rig to retrieve the pipe. A variation is to rest the pipe on the bottom cap, which you must reinforce.
Pre-install an anchor at the bottom of the casing. Simple prong anchors or packer types have been used. Slope Indicator has produced several prototypes of such anchors. Different soils may require different types of anchor.
- Pre-attach a weight to the bottom of the casing. This method requires a weight, a safety line to prevent casing from sinking, a borehole drilled deeper to accommodate the weight, and calculation of the uplift force. It is best used in shallow boreholes.
- Grout the borehole in stages. The uplift force of grout varies with the height of the grout column. If the column is short, the uplift force is low and the casing can be held in place by its own weight or with very little down-force applied from the top. When the grout sets, the bottom cap is isolated from the column of grout and there is no surface for the uplift force to act on. No more than two or three meters to 3 m need to be grouted in the first stage. If the normal bentonite/cement grout is used it needs to set for at least 12 hours before second-stage grouting. Avoid use of a quick-set grout, since the heat of hydration could melt and deform the plastic. The two stages can be placed via an outside tremie pipe. Alternatively the first stage can be placed before lowering the casing, provided that all is done efficiently so that there is no chance of the grout setting prematurely. If grout valve method is used, first stage grouting can be done through the valve, and then the valve is abandoned. An outside tremie pipe for the second stage is lowered with the casing, with its bottom at the level planned for the top of the first stage. After first stage grouting, the excess is flushed out via the tremie pipe, and then this is raised until the first stage has set.
- Fill the casing with drilling fluid that is heavier than the grout. This is a sure and easy method, but requires disposal of the drilling fluid.
Datasheet and Documents
Please download the data sheet for Inclinometer Casing.
You may also be interested in:
Read the INCLINOMETER CASING FAQ
When you buy inclinometer casing, important features to consider are:
Inclinometer Casing Part Numbers
QC CASING 85MM · 3.34" | |
---|---|
Casing Section, 10' (3.05 m) | 51150310 |
Casing Section, 5' (1.52 m) | 51150311 |
Section, Telescoping | 51150320 |
Cap, Bottom | 51150330 |
Cap, Bottom, Heavy Duty | 51100520 |
Grout Valve, Gasket Type | 51100830 |
Cap, Top | 51100500 |
Cap, Locking | 51100550 |
Splice Kit, Male | 51150350 |
Splice Kit, Female | 51150351 |
QC CASING 70mm · 2.75" | |
---|---|
Casing Section,10' (3.05 m) | 51150210 |
Casing Section, 5' (1.52 m) | 51150211 |
Section, Telescoping | 51150220 |
Cap, Bottom | 51150230 |
Cap, Bottom, Heavy Duty | 51101520 |
Grout Valve, Gasket Type | 51100820 |
Cap, Top | 51101500 |
Cap, Locking | 51101550 |
Splice Kit, Male | 51150250 |
Splice Kit, Female | 51150251 |
STANDARD CASING 85mm · 3.34" | |
---|---|
Casing Section, 10' (3.05 m) | 51100100 |
Casing Section, 5' (1.52 m) | 51100105 |
Telescoping Section | 51106400 |
Coupling | 51100200 |
Cap, Bottom, Heavy Duty | 51100520 |
Grout Valve, Gasket Type | 51100830 |
Cap | 51100500 |
Cap, Locking | 51100550 |
Pop Rivet AD44H | 51103301 |
STANDARD CASING 85mm · 3.34" | |
---|---|
Casing Section, 10' (3.05 m) | 51100100 |
Casing Section, 5' (1.52 m) | 51100105 |
Telescoping Section | 51106400 |
Coupling | 51100200 |
Cap, Bottom, Heavy Duty | 51100520 |
Grout Valve, Gasket Type | 51100830 |
Cap | 51100500 |
Cap, Locking | 51100550 |
Pop Rivet AD44H | 51103301 |
STANDARD CASING 70mm · 2.75" | |
---|---|
Casing Section, 10' (3.05 m) | 51101100 |
Casing Section, 5' (1.52 m) | 51101105 |
Telescoping Section | 51107400 |
Coupling | 51101200 |
Cap, Bottom, Heavy Duty | 51101520 |
Grout Valve, Gasket Type | 51100820 |
Cap | 51101500 |
Locking Cap with Padlock | 51101550 |
Pop Rivet AD42H | 51003303 |
EPIC CASING 70mm · 2.75" | |
---|---|
Casing Section, 10' (3.05 m) | 51111100 |
Coupling | 51111200 |
Telescoping Coupling | 51111400 |
Cap, Bottom, Heavy Duty | 51101520 |
Grout Valve, Gasket Type | 51100820 |
Cap | 51111500 |
Locking Cap with Padlock | 51101550 |
Pop Rivet AD46H | 51003310 |
Lubricant for Telescoping Coupling | 57504000 |
CPI CASING 85mm · 3.34" | |
---|---|
Casing Section, 10' (3.05 m). | 57500100 |
Casing Section, 5' (1.52 m) | 57500105 |
Telescoping Section | 57506400 |
Coupling with 2 Shear Wires | 57500200 |
Cap with Shear Wire | 57500500 |
Cap, Bottom, Heavy Duty | 51100520 |
Grout Valve, Gasket Type | 51100830 |
Cap, Top | 51100500 |
Spare Nylon Shear Wire | 57500700 |
O-Ring Lubricant | 57504000 |
CPI CASING 70mm · 2.75" | |
---|---|
Casing Section, 10' (3.05 m) | 57501100 |
Casing Section, 5' (1.52 m) | 57501105 |
Telescoping Section | 57507400 |
Coupling with 2 Shear Wires | 57501200 |
Cap with Shear Wire | 57501500 |
Cap, Bottom, Heavy Duty | 51101520 |
Grout Valve, Gasket Type | 51100820 |
Cap, Top | 51101500 |
Spare Nylon Shear Wire | 57501700 |
O-Ring Lubricant | 57504000 |
CPI CASING 48mm · 1.9" | |
---|---|
Casing Section, 5' (1.52 m) | 57502105 |
Coupling with 2 Shear Wires | 57502200 |
Cap with Shear Wire | 57502500 |
Grout Valve, Gasket Type | 57503700 |
Cap, Top | 51102500 |
Spare Nylon Shear Wire | 57502700/td> |
O-Ring Lubricant | 57504000 |
SHEAR WIRE CASING 85mm · 3.34" | |
---|---|
10' (3.05 m) Casing Section | 51160310 |
5' (1.52 m) Casing Section | 51160311 |
Section, Telescoping | 51160320 |
Cap, Bottom | 51160330 |
Cap, Bottom, Heavy Duty | 51100520 |
Grout Valve, Gasket Type | 51100830 |
Cap, Top | 51100500 |
Cap, Locking | 51100550 |
SHEAR WIRE CASING 70mm · 2.75" | |
---|---|
Casing Section, 10' (3.05 m) | 51160210 |
Casing Section, 5' (1.52 m) | 51160211 |
Section, Telescoping | 51160220 |
Cap, Bottom | 51160230 |
Cap, Bottom, Heavy Duty | 51101520 |
Grout Valve, Gasket Type | 51100820 |
Cap, Top | 51101500 |
Cap, Locking | 51101550 |
CASING ANCHORS | |
---|---|
Casing Anchor, 85 mm (3.34") | 51104385 |
Casing Anchor, 70 mm (2.75") | 51104370 |
Anchor + Grout Valve, 85mm(3.34") | 51104485 |
Anchor + Grout Valve, 70mm(2.75") | 51104470 |
INSTALLATION ACCESSORIES | |
---|---|
Mastic Sealing Tape | 51003800 |
Vinyl Tape | 51003900 |
Duct Tape | 51004000 |
ABS Solvent Cement, 1/2 pint | 51103401 |
ABS Solvent Cement, 1 pint | 51103402 |
Pop Rivet Gun | 50100202 |
Casing Clamp | 50100200 |