July 31, 2024

Yes. The standard GeoFlex segment consists of five 2 feet nodes (10 feet total) that are connected electrically via a waterproof Seacon connector and mechanically via a pinned universal joint. Once the project is complete the system can be removed and broken down into its 10 feet segments (provided that the shear isn’t so great that they can’t be removed from the casing). Those segments can be used on another project and because each node is addressable, it doesn’t matter in what order the segments are installed on the next project. The Horizontal GeoFlex uses the same durable nodes and connectors with the same redeployment benefit on future projects